Agawam High School Building Project

The “new” Agawam High School building project is moving quickly.   Below is a link to the website that lists everything you need to know.

PROGRESS UPDATE:

  • Geothermal Wells - There are three rigs continuously drilling down to about five hundred feet.  More than half of the 150 wells are dug, with approximately three per day completed.

  • The project is free of fossil fuels and the wells will serve as the source for heating and cooling the new building.

  • Foundation progress - significant progress is taking place. Footings have been poured and rebar /forms are going up daily.  Several large concrete trucks will then pour the walls soon.

  • All bids for steel are complete and some are arriving soon.  

  • At some point in October you will see the framing of the community wing.

  • Structural Steel: During the first week of October the structural steel will be delivered and it will go up soon after.

Construction progress