Agawam High School Building Project
The “new” Agawam High School building project is moving quickly. Below is a link to the website that lists everything you need to know.
PROGRESS UPDATE:
Geothermal Wells - There are three rigs continuously drilling down to about five hundred feet. More than half of the 150 wells are dug, with approximately three per day completed.
The project is free of fossil fuels and the wells will serve as the source for heating and cooling the new building.
Foundation progress - significant progress is taking place. Footings have been poured and rebar /forms are going up daily. Several large concrete trucks will then pour the walls soon.
All bids for steel are complete and some are arriving soon.
At some point in October you will see the framing of the community wing.
Structural Steel: During the first week of October the structural steel will be delivered and it will go up soon after.